Construction commenced

Issued date
10 October 2024

Stay up-to-date with our latest news

Learn more about news from QRO that relates to the areas you’re interested in.

Subscribe to emails

HomeBuilder grant

The date construction commenced for:

  • building a home—is the date excavation and site preparation work began
  • buying a home—is the date excavation and site preparation work began
  • renovating an existing home—is the date building work began
  • demolishing and building a home (combined contract)—is the date demolition work began
  • demolishing and building a home (separate contracts)—is the date building work began under the contract to build.